No live infrastructure touched -- decision-record edits only. Closes Stage 0 of docs/dc-dc-deployment-workflow.md, the gate blocking real Phase-0/1/2 work since the DC-DC design was drafted this same day.
FILES: docs/design-decisions.md (11 status-line updates + D-101 amendment + D-102 merge), docs/dc-dc-buildout-design.md (Section 10 rewritten as a ruling record, Section 3's Ceph gate annotated, stray "Section D-102" cross-reference corrected to D-101), docs/session-ledger.md (machine-derived block re-seeded, narrative entry).
WHAT: operator ruled on the buildout design's 6 redline items (via two AskUserQuestion rounds, live) and on each of D-100 through D-110 individually, per this repo's own discipline ("present options, do not implement" until ruled -- this delivery is the ruling, not a unilateral implementation).
Redline rulings:
tc netem link profile: same-metro dark-fiber lean, confirmed; re-tune when a specific Roosevelt inter-DC target is known.Per-decision disposition, docs/design-decisions.md:
MERGED INTO D-101 (2026-07-09, operator ruling). Body text LEFT IN PLACE, per this repo's append-only decision-record discipline -- the entry is retained for numbering/history, not deleted; D-101 is now the current, authoritative text for this sub-policy.VERIFIED, not just asserted: bash scripts/ledger-scan.sh's "PROPOSED / OPEN decisions" list no longer contains any of D-100 through D-110 -- only D-068 and D-071 remain (pre-existing, unrelated to this gate). repo-lint.sh: 0 fail / 1 documented legacy warn (unchanged). tests/repo-lint harness: 34/34 (unchanged -- no script logic touched, decision-record content only).
docs/dc-dc-deployment-workflow.md's Stage 0 banner and summary table, plus the companion visual tracker, updated to reflect Stage 0 CLEARED (see the companion Artifact redeploy).
REVERT: git checkout HEAD~ -- docs/design-decisions.md docs/dc-dc-buildout-design.md docs/session-ledger.md (re-opens Stage 0 -- not recommended; if a specific ruling needs reconsidering, amend that one decision's entry instead of reverting the whole ratification).
Stage 0 cleared -- Stage 1 (Phase 0: vcloud host prep) and onward can now proceed on runbook/tooling authorship without an open-decision blocker. Real values still pending NetBox assignment (DC2's supernet, the org ULA /48, per-DC GUA carve) and infrastructure access (a tofu/qemu-img/ ISO-tool-capable machine, a real vcloud host) remain separate, non-decision blockers -- tracked in the tooling gap register, not this ratification.