GA-R5 ruling: the D-139 GUA carve is sequenced BEFORE the Stage-5 deploy
Operator answer, exact utterance: "Apex push AND the MAAS/node GUA carve, then deploy". D-139 execution steps 1-3 run before the bundle deploy, so the cloud is deployed once on its final GUA addresses and nothing is re-addressed underneath it. The 2026-07-30 standing directive is satisfied in substance rather than literally. Recorded, not inferred: steps 4-6 were NOT put, and step 6 has a deploy coupling this ruling does not settle -- the per-DC VIP overlays carry v6 VIPs in the ULA range, so deploying after steps 1-3 alone leaves GUA nodes with ULA VIPs. Own exchange owed before Step 4. Neither ruling A nor B is touched; no new D-number (GA-R3: OPS). Co-Authored-By: Claude Opus 5 (1M context) <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01HvCyrwvYTTcDYnRErfMsNf |
|---|
|
|
| docs/CURRENT-STATE.md |
|---|
| docs/design-decisions.md |
|---|