History for openstack-caracal-dc-dc / docs / CURRENT-STATE.md
2026-07-20
@JANeumatrix
CORRECTION (GA-R1/C2): D-125 rack-bridge follow-up was CONFOUNDED, not evidence ...
JANeumatrix committed 1 day ago
@JANeumatrix
D-125 egress gate executed (throwaway VM, as ruled): bridge-in PROVEN, upstream NAT egress fails -- gate OPEN pending one sudo measurement ...
JANeumatrix committed 1 day ago
@JANeumatrix
DC edge bootstrap: D-112(c) console chain complete + API key minted; D-113(a2) PROVEN on 26.7 ...
JANeumatrix committed 1 day ago
@JANeumatrix
Deploy step C COMPLETE: inner apply 28/28 from voffice1, converged zero diff; 9 nodes + 26.7 edge RUNNING at depth-4; three first-real-apply fixes ...
JANeumatrix committed 1 day ago
@JANeumatrix
Deploy step B COMPLETE: rack bootstrapped + enrolled, SEC-010 CLOSED both ends (operator-ruled), OPNsense 26.7 base staged (operator-ruled); ledger-scan fail-open hardening ...
JANeumatrix committed 1 day ago
@JANeumatrix
Step B transit reach ESTABLISHED: voffice1 .1/30 applied (Kea re-key incident fixed); vvr1-dc0 netplan set-name root cause fixed; zero-diff converged ...
JANeumatrix committed 1 day ago
2026-07-19
@JANeumatrix
Step B prereq: voffice1 transit NIC authored (172.31.0.1/30 region end, D-124); ruling recorded; expected plan 1/1/1 ...
JANeumatrix committed 1 day ago
@JANeumatrix
DC0 deploy STEP A EXECUTED: outer apply 6/0/6 exact; G8+G9 CLOSED; convergence zero ...
JANeumatrix committed 2 days ago
@JANeumatrix
AUDIT EXIT: operator re-signed CURRENT-STATE; G3+G11 CLOSED, G9 OPEN; session close (GA-R4) ...
JANeumatrix committed 2 days ago
@JANeumatrix
Batch 6 item 3: exit probe trio 21/21 -- 7/7 on ALL THREE (bar exceeded) ...
JANeumatrix committed 2 days ago
@JANeumatrix
Batch 6: exit runs 1/2/4/5 -- archive exclusion (operator-ruled), adjudication, plan==triple, S2 ...
JANeumatrix committed 2 days ago
@JANeumatrix
Batch 5: skill sweep -- GA-R1..R7 implemented in openstack-cloud-ops (single commit) ...
JANeumatrix committed 2 days ago
@JANeumatrix
Batch 4 C6: docs disposition -- 24 history docs archived, 16 retained, refs rewritten ...
JANeumatrix committed 2 days ago
@JANeumatrix
Batch 3 CLOSE: memory hygiene (GA-F05..F08 memory surfaces) + G1 review; GA-F16 registered ...
JANeumatrix committed 2 days ago
@JANeumatrix
Batch 2 CLOSE: verification + adjudication recorded; last GA-F03 site fixed ...
JANeumatrix committed 2 days ago
@JANeumatrix
GA-F10/H1 + GA-R1/R6: token migration, State-line demotions, E1 type tags (2.5+2.6) ...
JANeumatrix committed 2 days ago
@JANeumatrix
G6 reconcile EXECUTED (state surgery, operator-ruled) + G7 triple 6/0/6 recorded ...
JANeumatrix committed 2 days ago
@JANeumatrix
D-130 ADOPTED (a) + implemented: seed-volume ignore_changes guard (GA-F01, G4+G5 CLOSED) ...
JANeumatrix committed 2 days ago
@JANeumatrix
Batch 1 open: L10 status-coupling flipped WARN -> FAIL (GA-R1/C1) ...
JANeumatrix committed 2 days ago
@JANeumatrix
Batch 0 CLOSE: verification green; session changelog + ledger entry ...
JANeumatrix committed 2 days ago
@JANeumatrix
Batch 0.4: extractor status scan keyed to the legal token set (GA-F10 / vocab H1) ...
JANeumatrix committed 2 days ago
@JANeumatrix
Batch 0.3: ledger-scan wrap-aware next-free exclusion (GA-F15) ...
JANeumatrix committed 2 days ago
@JANeumatrix
Batch 0.2: ledger-scan SEC reporting repointed at security-ledger.md (GA-R4/F3) ...
JANeumatrix committed 2 days ago
@JANeumatrix
Batch 0.1: repo-lint gains L10 status-coupling check (GA-R1 rule 8 / C1) ...
JANeumatrix committed 2 days ago
2026-07-18
@JANeumatrix
Sweep plan AMENDED per external review (S1-S5, single commit); G3 row updated ...
JANeumatrix committed 2 days ago
@JANeumatrix
GA Phase-5 sweep plan DRAFTED (batches 0-6, GA-F/GA-R traced, dependency-ordered) ...
JANeumatrix committed 2 days ago
@JANeumatrix
Vocabulary RATIFIED: Option A + H1 (utterance quoted) -- PHASE 4 COMPLETE; G2 CLOSED ...
JANeumatrix committed 2 days ago
@JANeumatrix
GA-R7 RATIFIED (operator, amendments G1+G2+G3, question+answer quoted); vocabulary A/B staged ...
JANeumatrix committed 2 days ago
@JANeumatrix
GA-R4 RATIFIED (operator, amendments F1+F2+F3, question+answer quoted); GA-R7 draft staged ...
JANeumatrix committed 3 days ago
@JANeumatrix
GA-R6 RATIFIED (operator, amendments E1+E2+E3, question+answer quoted); GA-R4 draft staged ...
JANeumatrix committed 3 days ago