This file is the VERBATIM record of what each read-only lens returned, kept separate from the synthesis so the synthesis can never quietly reshape a lens's claim. Findings are NOT yet verified here -- adversarial verification happens in the synthesis, and a finding that is refuted stays in this file with its refutation recorded, never deleted.

Schema each lens was required to use: ID / CLAIM / EVIDENCE / BLOCKS-STAGE-5 / DISPOSITION. Every lens was also required to report any denied or prompted tool call as UNMEASURED with the exact command, never folded into a negative finding.


LENS 3 -- DEPLOY-ARTIFACT CONFORMANCE (returned first)

ID: L3-1 CLAIM: preflight.sh P2 validates only the bare dc0 base bundle; the artifact Stage 5 actually deploys (base + the three dc1 overlays, dc1 bands) is validated by no gate at all -- and both inputs return PASS, so P2's green is not evidence about the dc1 deploy. EVIDENCE: scripts/preflight.sh:33 -- python3 scripts/provider-bundle-check.py bundle.yaml (no --overlay, no --dc). Measured bare: PASS: Pattern A / D-052-D-053 bundle invariants (bundle.yaml) EXIT=0. Measured full dc1 input (--overlay overlays/vr1-dc1-machines.yaml --overlay overlays/vr1-dc1-vips.yaml --overlay overlays/dc-ha-scaleup.yaml --dc vr1-dc1): also PASS EXIT=0 (109 relations well-formed, placement: role-separated (3 control/2 compute/4 storage)). Nothing in scripts/preflight.sh ever passes an overlay or --dc. BLOCKS-STAGE-5: yes | DISPOSITION: DOCFIX

ID: L3-2 CLAIM: designate is a SECOND app (beyond the known vault case) with full HA intent and no VIP anywhere in the tracked tree -- scaled to 3, ha bound, designate-hacluster related and set to cluster_count: 3 -- and the checker passes it because its VIP loop continues on a missing vip. EVIDENCE: bundle.yaml:830-847 (designate stanza: ha: metal-internal, no vip:); bundle.yaml:940 designate-hacluster: {... cluster_count: 1 ...}; bundle.yaml:1106 - [designate:ha, designate-hacluster:ha]; overlays/dc-ha-scaleup.yaml:128-130 (designate: num_units: 3) and :172 (designate-hacluster: {options: {cluster_count: 3}}). grep -n 'vip' bundle.yaml returns exactly 11 lines (200, 239, 295, 364, 400, 490, 576, 603, 657, 722, 780) -- none for designate, none for vault. scripts/provider-bundle-check.py:133-135: vip = ...get("vip"); if not vip: continue. D-136's recorded problem statement (docs/design-decisions.md:4786-4789) names only vault for this defect. BLOCKS-STAGE-5: yes | DISPOSITION: ruling

ID: L3-3 CLAIM: runbooks/dc-dc-phase4-juju-bundle-per-dc.md Step 4 -- the Stage-5 deploy step -- names ZERO --overlay flags and instructs the opposite of the authored dc1 artifacts; following it verbatim deploys dc0's VIPs and dc0's machine tags into the dc1 model. EVIDENCE: runbooks/dc-dc-phase4-juju-bundle-per-dc.md:203 -- "DC1: deploy the EXISTING bundle.yaml with NO VIP edits"; :210 -- "DC2: BLOCKED until its VIP band exists ... bundle.yaml's VIP lines need editing ... a genuine, reviewed bundle edit". Neither overlays/vr1-dc1-vips.yaml, overlays/vr1-dc1-machines.yaml, overlays/dc-ha-scaleup.yaml nor overlays/dc-dc-ipv6-family-matrix.yaml is mentioned anywhere in that runbook. dc1's band IS ratified and IS authored (overlays/vr1-dc1-vips.yaml:16-46, 10.12.64/68/72 .50-.60), so the "BLOCKED" line contradicts on-disk state; and the "edit bundle.yaml" instruction contradicts the recorded operator utterance at docs/design-decisions.md:4930-4936 ("Base bundle and everything else is applied via overlay"). BLOCKS-STAGE-5: yes | DISPOSITION: DOCFIX

ID: L3-4 CLAIM: The 10th Juju-controller VM is UNAUTHORED, not merely un-applied -- no OpenTofu resource, no script, no runbook step exists for it anywhere; only prose describes it. EVIDENCE: opentofu/vr1-dc1-substrate/main.tf locals declares exactly 9 node keys (control-01..03, compute-01..02, storage-01..04); grep -in "controller" opentofu/vr1-dc1-substrate/*.tf -> zero hits; module blocks are inner_storage, vr1_dc1_planes, vr1_dc1_wan, vr1_dc1_opnsense, vr1_dc1_node -- no controller module. grep -rn "juju-controller-vr1-dc1" opentofu/ runbooks/ scripts/ bundle.yaml overlays/ -> zero hits; the string exists only in docs/CURRENT-STATE.md:187, docs/design-decisions.md:2160-2161, and audit files. bundle.yaml:78 carries only the comment "The Juju CONTROLLER is a dedicated 10th VM (D-104 amendment) ... NOT a bundle machine". docs/CURRENT-STATE.md:179-180's "10th node is ADDITIVE (1 add/0/0)" is therefore a projection with no resource behind it. BLOCKS-STAGE-5: yes -- dc-dc-phase4 Step 2 juju bootstrap has no target machine. | DISPOSITION: DOCFIX

ID: L3-5 CLAIM: Per-role MAAS tags (Fork 3) are consumed by the machines block but authored nowhere in the repo; the only tag-creation code creates ONE tag, and the only runbook guidance still points at the retired DC0 literal openstack. Deploy fails hard at allocation (it does not silently mis-place). EVIDENCE: Consumers -- bundle.yaml:81-97 and overlays/vr1-dc1-machines.yaml:23-39: every machine constrains on TWO tags, tags=openstack-vr1-dc1,<control|compute|storage>. Producers -- the only tag-create in the tree is scripts/reenroll-hosts.sh:177-180 (maas ... tags create name="$HOST_TAG", a single tag). Runbook -- runbooks/dc-dc-phase3-maas-enlist-deploy.md:289-302 still says lib-hosts.sh's HOST_TAG="openstack" is DC0's literal and shows tag update-nodes "<confirmed-tag>", singular. Nothing anywhere creates control/compute/storage. Juju passes tags= to MAAS as an allocation constraint; an unmatched tag yields no candidate machine. BLOCKS-STAGE-5: yes | DISPOSITION: DOCFIX

ID: L3-6 CLAIM: pre-flight-checks.sh (preflight P4) asserts two carve facts that D-133 RULED cannot exist on ANY VR1 DC -- stronger than the known "VR0-frozen" framing: two checks contradict a RULED decision and can never pass on dc0 or dc1, and D-133's own affected-surfaces list omits the file. EVIDENCE: scripts/pre-flight-checks.sh:128 (metal-internal VID=$mivid (want $METAL_INTERNAL_VID)); :143-144 ($h metal-internal on '$ifname' (want $METAL_INTERNAL_IFACE)). Values come from VR0 defaults scripts/lib-net.sh:44-45 (METAL_INTERNAL_VID="103", METAL_INTERNAL_IFACE="br-internal") because grep -n lib_net_select_dc scripts/pre-flight-checks.sh returns zero hits. D-133 (docs/design-decisions.md:4562-4566): "no br-metal.103 / br-internal stack exists in VR1. VID 103 is a VR0-only fact." D-133's affected-surfaces list (:4587-4592) does not name pre-flight-checks.sh. BLOCKS-STAGE-5: yes | DISPOSITION: DOCFIX

ID: L3-7 CLAIM: The dc1 arm of lib-net.sh UNSETS the VIP constants any DC-aware CHECK 1 would need, while leaving the octet bounds set -- so the data for the fix does not exist yet; and VIP_OCTET_MAX lives in lib-net.sh, not in provider-bundle-check.py (whose equivalents are OCTET_LO/OCTET_HI). EVIDENCE: Measured -- . scripts/lib-net.sh; lib_net_select_dc vr1-dc1 -> VIP_PREFIX_PROVIDER=[UNSET] ADMIN=[UNSET] INTERNAL=[UNSET] MIN=[50] MAX=[60] COUNT=[UNSET]. Source scripts/lib-net.sh:157 unsets them; :54-59 holds the VR0 values. scripts/provider-bundle-check.py:41 uses separately-named OCTET_LO, OCTET_HI = 50, 60, so raising the band is a TWO-file change. BLOCKS-STAGE-5: yes | DISPOSITION: DOCFIX

ID: L3-8 CLAIM: The base bundle.yaml -- documented as the vr1-dc0 source of truth -- carries dc1's compute MACs in ovn-chassis bridge-interface-mappings, and no dc0 counterpart overlay exists; the checker cannot catch it because the role-separated branch only asserts "well-formed MAC". EVIDENCE: bundle.yaml:458-464 -- comment "VR1 dc1: the 2 compute nodes' provider-public (enp2s0) MACs", values br-ex:52:54:01:d1:04:02 / br-ex:52:54:01:d1:05:02, pinned to vr1-dc1 in opentofu/vr1-dc1-substrate/main.tf:113-118. dc0 uses 52:54:00:* (scripts/lib-hosts.sh:121-122). overlays/vr1-dc1-machines.yaml:7-8 states "The base bundle.yaml is the vr1-dc0 source of truth". Checker: scripts/provider-bundle-check.py:167-172 only counts well-formed MACs under role_sep. BLOCKS-STAGE-5: no for a dc1-first Stage 5 (values happen to be dc1's); yes for any dc0 deploy -- no local MAC match means ovn-chassis builds no br-ex mapping and provider egress is dead on dc0 compute, with no gate failing. | DISPOSITION: DOCFIX

ID: L3-9 CLAIM: The D-101 two-overlay vip: collision is order-dependent in BOTH directions, measured: one order hard-fails, the other silently drops every v6 leg. EVIDENCE: ipv6 overlay LAST -> EXIT=1, ten [FAIL] <app> vip not a triple: '{{KEYSTONE_VIP_PROVIDER_V4}} ...' plus [ok] 1 clustered VIP(s) are ... triples (only octavia survives; the ipv6 overlay omits it -- overlays/dc-dc-ipv6-family-matrix.yaml:140-152). Reverse order (vips overlay last) -> v6 legs replaced wholesale, merged doc is a PASS with pure-v4 triples, no checker reports the loss. Merge semantics: scripts/provider-bundle-check.py:52-58 _deep_merge -- options.vip is a scalar, REPLACED last-wins. BLOCKS-STAGE-5: yes | DISPOSITION: ruling

ID: L3-10 CLAIM: ceph-osd is the only application carrying an app-level MAAS tag constraint, and it is the retired bare VR0 tag openstack. EVIDENCE: bundle.yaml:567 -- constraints: arch=amd64 tags=openstack. grep -n 'tags=' bundle.yaml returns ten lines: nine machines-block entries (:81-97, all tags=openstack-vr1-dcN,<role>) plus :567. D-119 retires bare selectors (scripts/lib-net.sh:161). Live MAAS has no openstack tag. BLOCKS-STAGE-5: no -- ceph-osd has explicit to: ["5","6","7","8"], so the constraint is not used for selection. Latent reject if placement is removed. | DISPOSITION: DOCFIX

ID: L3-11 CLAIM: overlays/octavia-pki.yaml's absence is BY DESIGN -- a gitignored secret regenerated per deploy; preflight P4's failure on it is the intended pre-deploy prompt. EVIDENCE: .gitignore:40; git ls-files overlays/ returns only four tracked overlays; scripts/pre-flight-checks.sh:64-71 fail message says "place it or regenerate via runbook Step 1.0-GEN before deploy"; docs/design-decisions.md:5099 records it as an "Accepted residual". Residual doc defect: README.md:35 still says "overlays/ empty in git -- the only overlay (octavia-pki.yaml)", now four overlays stale. BLOCKS-STAGE-5: no | DISPOSITION: log-only

ID: L3-12 CLAIM: A programmatic duplicate-key scan of bundle.yaml and all four overlays found ZERO duplicate keys at any nesting level -- the BUNDLEFIX-052 class is clean -- and the detector was self-tested to prove it can fail. EVIDENCE: Custom yaml.SafeLoader subclass reporting repeated keys per node, run over bundle.yaml + overlays/*.yaml: no-duplicate-keys on all five. Self-test against a planted document: SELF-TEST planted-dup findings: [(9, 'keystone'), (7, 'bindings')] -- fires at both nesting levels. NOTE: no repo gate performs this scan; it exists only as this session's ad-hoc script, so the class can regress undetected (provider-bundle-check.py:106 uses plain yaml.safe_load, which silently take-lasts). BLOCKS-STAGE-5: no | DISPOSITION: log-only

ID: L3-13 CLAIM: Six applications added 2026-07-10 (D-106 designate / D-108 replication) have no row in the as-built version lock, so their channel pins have no lock authority behind them. EVIDENCE: Set-difference of bundle.yaml applications against runbooks/appendix-B-asbuilt-version-lock.md rows: in bundle not in appendix-B: ['ceph-rbd-mirror', 'cinder-backup', 'designate', 'designate-bind', 'designate-hacluster', 'designate-mysql-router']; in appendix-B not in bundle: []. Every other application's channel matches appendix-B exactly. NOT verified against Charmhub -- see UNMEASURED. BLOCKS-STAGE-5: no | DISPOSITION: log-only

ID: L3-14 CLAIM: Affirmative conformance -- the items checked that PASS, recorded so they are not re-litigated downstream. EVIDENCE: D-121 Option C -- bundle.yaml:80-97 gives 3 control / 2 compute / 4 storage; checker confirms placement: role-separated ...; anti-affinity + role placement + counts OK on the merged dc1 input; nova-compute num_units: 2 to: ["3","4"] (:322-323), ceph-osd num_units: 4 to: ["5","6","7","8"] (:556-557). D-108 replication bindings intact post-BUNDLEFIX-052 (:545, :911-913, relation :1046). D-100 provider-raw (:456 ovn-bridge-mappings: physnet1:br-ex). D-133 flat carve -- no VLAN/VID construct anywhere in bundle.yaml. No application binds public: provider-vip. bash tests/provider-bundle-check/run-tests.sh -> PASS=15 FAIL=0, including T15 (dc1 VIPs vs dc0 bands FAILS), so the --dc arm is proven capable of failing. BLOCKS-STAGE-5: no | DISPOSITION: log-only

ID: L3-15 CLAIM: Three artifact references in bundle.yaml comments point at files that do not exist, and one comment states the wrong plane CIDR. EVIDENCE: bundle.yaml:654 --overlay overlays/vr0-dc0-testcloud.yaml (no such file); bundle.yaml:15, overlays/dc-ha-scaleup.yaml:11, overlays/dc-dc-ipv6-family-matrix.yaml:11 reference overlays/${DC}-hostnames.yaml (proposed only, docs/dc-dc-deployment-workflow.md:257, never authored); bundle.yaml:35 says geneve overlay is on 10.12.12.0/22 but measured from lib-net.sh that is metal-internal and dc0's data-tenant is 10.12.16.0/22. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

LENS 3 UNMEASURED

  1. Juju overlay-merge semantics for the machines: block. command -v juju -> NOT on PATH on this jumphost. provider-bundle-check.py:60-65 merges with a MIRROR of juju's documented behaviour, not juju itself, so the MODE-2 PASS is evidence about the mirror, not about juju. Not run: juju deploy ./bundle.yaml --overlay ... --dry-run -m <dc1-model>.
  2. Charm option existence for prefer-ipv6, min-cluster-size, and hacluster's cluster_count semantics -- not fetched from Charmhub or charm source; the overlays carry their own VERIFY-AT-DEPLOY caveats.
  3. Charmhub currency of the six unlocked channels in L3-13. No upstream fetch performed.
  4. dc0's compute-node provider-public (enp2s0) MACs -- lib-hosts.sh records only dc0 BOOT MACs; no authored dc0 provider-NIC MAC found anywhere. What dc0's correct values ARE is unmeasured.
  5. preflight.sh / pre-flight-checks.sh end-to-end execution -- not run by this lens; its P4 findings are read from source.
  6. Live MAAS tag state -- used the measured list supplied in the brief; ran no maas command.

LENS 6 -- STAGES 6-7 PRE-MORTEM (returned second)

ID: L6-1 CLAIM: bundle.yaml already carries live designate/designate-bind/designate-mysql-router/designate-hacluster blocks + 8 relations (DOCFIX-167), so Stage 5's juju deploy WILL deploy Designate -- which makes Stage 7 Step 5's gate ("the diff shows ONLY the new designate/... applications being added") unsatisfiable, and Stage 5 Step 4's own statement false. EVIDENCE: bundle.yaml:830,849,858,940 + :1099-1106 (8 relations); docs/dc-dc-deployment-workflow.md:531-542 (DOCFIX-167 CLOSED 2026-07-10). Contradicted by runbooks/dc-dc-phase4-juju-bundle-per-dc.md:215-217 ("bundle.yaml explicitly ships \"NO designate\" ... Designate reactivation is Stage 7's job (D-106), do not reactivate it mid-Stage-5") and runbooks/dc-dc-phase6-designate-cos-magnum.md:359-370 GATE. BLOCKS-STAGE-5: yes | DISPOSITION: ruling -- (A) suppress designate for the Stage-5 deploy (subtractive overlay / rendered per-stage bundle), keeping Stage 7's incremental-add shape, or (B) accept Designate landing at Stage 5 and rewrite Stage 7 Steps 1/5 to "configure, not deploy". NOTE: D-106's own bootstrap order puts os-public-hostname+FQDN-SAN certs BEFORE Designate; option (B) inverts that order.

ID: L6-2 CLAIM: dc-dc-teardown-rollback.md Step 2 now routes to a FALSE CLEAR -- it decides "nothing to clean up in MAAS" by reading a vm_host, but the VR1 DCs deliberately have NO MAAS pod (power_type=virsh per machine, D-103/D-123 amendments) while 18 nodes ARE enrolled; the check returns empty, the runbook says skip, and the containment VM gets destroyed out from under 18 live MAAS records. EVIDENCE: runbooks/dc-dc-teardown-rollback.md:160-176 ("If this returns nothing (expected for any VR1 site before Stage 4 has run for it): skip to Step 3, there is nothing to clean up at this layer yet") and :101-110 ("this repo has not yet reached Stage 4 ... for any VR1 DC"). Both now false: docs/CURRENT-STATE.md:47-48 (18 nodes READY); docs/audit/stage4-discovery-20260723.txt:2-5 shows vvr1-dc0 7chphy / vvr1-dc1 nmpcq4 are RACK CONTROLLERS, not vm-hosts. Related hazard already indexed but not referenced here: runbooks/appendix-A-troubleshooting.md:781. BLOCKS-STAGE-5: yes -- Stage 5 is the first stage that can fail partway with a live cloud on top, and this runbook is the documented reach-for at that moment. | DISPOSITION: DOCFIX

ID: L6-3 CLAIM: dc-dc-teardown-rollback.md Step 3's scoped-destroy command names five OpenTofu modules that exist in neither root, so the Path A rollback is not executable; its header also still declares the tree unvalidated for a reason no longer true. EVIDENCE: :192-206 targets module.dc1_maas_vm_host, module.dc1_opnsense, module.dc1_node_01, module.dc1_node_02, module.dc1_storage, module.dc1_planes, and admits at :205-206 that a -target naming a nonexistent module errors. Actual outer modules: vr1_dc0_storage(35), vr1_dc1_storage(49), office1_*, mesh_vr1_dc0_vr1_dc1(125), netem_...(353), vr1_dc0_uplink(379), vr1_dc1_uplink(391), vvr1_dc0(410), vvr1_dc1(537). Inner: vr1_dc0_planes(34), vr1_dc0_wan(51), vr1_dc0_opnsense(60), vr1_dc0_node(136). Step 4's VERIFY (:242-245) greps vcloud virsh for DC domains that live INSIDE vvr1-dc0, and grep -i dc1 now matches the SECOND DC. Header :13-19 still says no tofu binary was ever available -- contradicted by docs/CURRENT-STATE.md:857. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

ID: L6-4 CLAIM: If dc-ha-scaleup.yaml is applied at Stage 5, ceph-radosgw and designate deploy at 3 units per DC -- but Stage 6's radosgw multisite procedure and the DOCFIX-165 script are single-unit-shaped, so realm/period membership lands on one of three gateways and Step 4's gate can false-green. EVIDENCE: overlays/dc-ha-scaleup.yaml:132-133, :128-129, :171-172. Against runbooks/dc-dc-phase5-dr-failover-drill.md:237-239 ("Restart the DC1 radosgw unit (juju run ceph-radosgw/0 restart)") and measured bash scripts/dc-dc-radosgw-multisite.sh --help -> master-init --dc vr1-dc0|vr1-dc1 --model M --unit U (single --unit, no all-units mode). Step 4's --endpoints=http://<DC1_RGW_ENDPOINT_TBD> is unit-vs-VIP unspecified. BLOCKS-STAGE-5: yes -- whether to apply the HA overlay is a Stage-5 deploy-time choice and scaling 1->3 afterwards is a live-cloud change. | DISPOSITION: ruling (apply HA overlay at Stage 5 or not) + DOCFIX (multi-unit radosgw path)

ID: L6-5 CLAIM: Stage 7's two STOP conditions keyed on "dc2's literals are not yet assigned" are reversed by later rulings -- an operator halts Stage 7 for vr1-dc1 on a gap that is closed, and the dc2 fail-loud they cite is now a RETIRED-SELECTOR failure. EVIDENCE: runbooks/dc-dc-phase6-designate-cos-magnum.md:285-288 and :536-539. Reversed by scripts/lib-net.sh:128-158 (real vr1-dc1 arm) and :160-163 (bare $dc RETIRED, D-119); docs/CURRENT-STATE.md:781-783 (dc1 addressing RATIFIED 2026-07-21); overlays/vr1-dc1-vips.yaml. Same defect in runbooks/dc-dc-phase4-juju-bundle-per-dc.md:82-93 ("STOP here for DC2"). BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

ID: L6-6 CLAIM: Stage 7 Step 10 presents COS-scrapes-the-edge as an unruled fork with "If out-of-scope, do nothing here" -- but D-129(i) was RULED in-scope 2026-07-21 and explicitly names this step's pin UNGATED. The DOCFIX-204 pattern exactly. EVIDENCE: runbooks/dc-dc-phase6-designate-cos-magnum.md:482-487. Reversed by docs/design-decisions.md:4228-4235 (utterance "In-scope, per-DC (Recommended)"; "the Step-10 pin ... is therefore UNGATED and lands at its pinned deployment step") and Status line :4203. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

ID: L6-7 CLAIM: Stage 6 Step 2's fallback wiring commands contradict the real charm metadata DOCFIX-167 recorded in bundle.yaml, and Step 2's governing DoD bullet is vacuous -- three wrong endpoint/placement shapes would be typed against a live cloud if that path is taken. EVIDENCE: runbooks/dc-dc-phase5-dr-failover-drill.md:153-158 deploys cinder-backup with --to lxd:<UNIT_NUMBER_TBD> and relates cinder-backup:amqp rabbitmq-server:amqp; :161-162 relates ceph-rbd-mirror:ceph-rbd-mirror ceph-mon:rbd-mirror. Against bundle.yaml:877-885 (cinder-backup is a SUBORDINATE requiring ceph/juju-info, no amqp; ceph-rbd-mirror requires ceph-local/ceph-remote) and actual relations :1032-1033, :1046. A subordinate takes no --to. DoD :631 and delivery checkbox :642-644 can never be ticked because bundle.yaml:545 already reads rbd-mirror: replication. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

ID: L6-8 CLAIM: The Stage-6 runbook is written entirely in retired DC1/DC2 labels and issues promote/demote commands against --os-cloud dc1 / --os-cloud dc2, where dc1 means the FIRST DC -- but under D-119 vr1-dc1 is the SECOND DC. An inverted-target hazard on commands the runbook says must never be reordered. EVIDENCE: runbooks/dc-dc-phase5-dr-failover-drill.md:116-118, :371, :505, :585. Against scripts/lib-net.sh:160-163 (bare selectors RETIRED, "AMBIGUOUS ACROSS REGIONS") and docs/dc-dc-deployment-workflow.md:143 (C3 done 2026-07-14, "every runbook call site"). Measured: bash scripts/dc-dc-dr-drill.sh --help -> failover --dc vr1-dc0|vr1-dc1 -- the scripts were migrated, the runbook was not, so it disagrees with the tool it tells you to prefer. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

ID: L6-9 CLAIM: Stage 6's entry condition requires Stage 5 to have delivered "Ceph-over-v6 and geneve-over-v6 verified", but Stage 5's Step 12 is contingent on an unapplied overlay and an unresolved Octavia IPv6 fork, and its text sanctions recording "blocked on Step 6" -- so Stage 5 can close without producing Stage 6's precondition. EVIDENCE: runbooks/dc-dc-phase5-dr-failover-drill.md:10-15. Against runbooks/dc-dc-phase4-juju-bundle-per-dc.md:354-358 and :290-297 ("Octavia's lb-mgmt-net IPv6 support is a real, open risk, not resolved ... Decide explicitly before this stage's ... gate is declared closed"). Register item 13: docs/dc-dc-deployment-workflow.md:639-647. BLOCKS-STAGE-5: yes -- the Octavia lb-mgmt-net v4-vs-v6 fork is a Stage-5 deploy-shape choice; deciding after Octavia is deployed is a live-cloud change, and GA-R6 E3 forbids a conditional close. | DISPOSITION: ruling

ID: L6-10 CLAIM: Both Stage 5 and Stage 7 issue juju deploy --overlay "overlays/${DC}-hostnames.yaml" against a file that does not exist and whose proposed name does not match the interpolation. EVIDENCE: ls overlays/ -> four files, no *-hostnames.yaml. Referenced as a live --overlay argument at runbooks/dc-dc-phase4-juju-bundle-per-dc.md:277-281, runbooks/dc-dc-phase6-designate-cos-magnum.md:361-364 and :372-377, overlays/dc-ha-scaleup.yaml:9-13. Proposed filenames conflict: dc-dc-phase6:235-240 proposes overlays/dc1-hostnames.yaml / dc2-hostnames.yaml versus ${DC} = vr1-dc0/vr1-dc1 per D-119. BLOCKS-STAGE-5: yes -- Stage 5 Step 6's apply command references it. | DISPOSITION: DOCFIX

ID: L6-11 CLAIM: Gap-register item 17 is stale-OPEN in a way that produces a FALSE STOP: it states neither DC has an ISP-uplink network, but both uplinks are built and both D-125 egress gates PASSED. The skill's VR1 deploy loop says to read this register FIRST. EVIDENCE: docs/dc-dc-deployment-workflow.md:728-731. Against opentofu/main.tf:379, :391, opentofu/vr1-dc0-substrate/main.tf:51, docs/CURRENT-STATE.md:845 (D-125 PASS 2026-07-20) and the G12 row (D-125 PASS 2026-07-22 dc1). Same class: gap 15 (:678-685) still says "DC2 is still blocked at the network-selector layer" and that the per-DC artifact mirror "has no identified owning stage/module" though D-135 owns it; gap 11's netem sub-item (:595-600) predates the 2026-07-21 standing-placeholder ruling and the live apply on virbr5. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

ID: L6-12 CLAIM: The gap register has TWO items numbered 19, and the second declares itself OPEN and a hard precondition of Stage 3 OpenTofu work -- a condition closed by D-119 on 2026-07-14. EVIDENCE: docs/dc-dc-deployment-workflow.md:787 (item 19 CLOSED via DOCFIX-176) and :806 (a second item 19), whose :835-837 reads "Status: OPEN. It is Stage 2 close-out item C3 and the FIRST step of any Stage 3 OpenTofu work.". Closed by :143 and scripts/lib-net.sh:95-166. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

ID: L6-13 CLAIM: Register item 20 (durable host->site reach) is NOT satisfied on the record for EITHER DC -- the tool carries only a commented template row and no capture states the measured determination the DC-standup DoD requires. "No leg needed" is currently INFERRED, not measured. EVIDENCE: docs/dc-dc-deployment-workflow.md:867 ("Office1 CLOSED; DC rows DEFERRED-until-measured"); scripts/site-baseleg.sh:45-48 -- LEGS=( [office1]=... # [vr1-dc0]="<net>|<host-cidr>|<route-cidr>|<route-gw>" # MEASURE first ), no dc row live or commented for dc1. Obligation: runbooks/dc-dc-phase2-tofu-dc-substrate.md:748-752 DC-standup DoD item 1. Repo-wide grep of docs/audit/* and docs/archive/stage-records/* returns only the Office1 row. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX (record the measured verdict per DC, or add leg rows) -- the measurement is a session task, not a ruling.

ID: L6-14 CLAIM: Stage 6 Step 9 and its DoD bullet stake the D-104 control-plane restore drill on juju restore-backup, a command with zero corroboration anywhere in this repo and no verified existence on the Juju 3.6 client the drill will use. EVIDENCE: runbooks/dc-dc-phase5-dr-failover-drill.md:443-456 and DoD :624-625. Repo-wide grep -rn "restore-backup" returns ONLY those two lines; scripts/cloud-snapshot.sh:141 implements only juju create-backup. Juju is not installed here (docs/CURRENT-STATE.md:872), so the flag could not be verified. BLOCKS-STAGE-5: no -- but verification is cheap the moment a Juju client exists at Stage 5. | DISPOSITION: log-only (queue the Stage-5 first-Juju-client verification)

ID: L6-15 CLAIM: runbooks/README.md's VR1 track table -- the surface the skill routes an operator to for stage selection -- carries two claims contradicted by the as-built. EVIDENCE: runbooks/README.md:56 ("with VR0's own testcloud host becoming DC1") against docs/dc-dc-deployment-workflow.md:52-53 and opentofu/main.tf:410,537. runbooks/README.md:67 lists Stage 2 as building GitBucket against docs/dc-dc-deployment-workflow.md:85 ("GitBucket is NO LONGER A GATE (D-116)"). The VR0-vs-VR1 track separation itself is stated correctly at :53-61; no step routes an operator into the wrong track. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

LENS 6 CHECKED, NO FINDING

  • (d) Two-DCs-differ-by-ruling: no step in the phase-5/6 runbooks or the teardown runbook assumes an apt mirror at either DC (grep for mirror/apt/proxy/cache returns only rbd mirror / ceph-rbd-mirror hits). The D-135 asymmetry is correctly carried in the Stage-5 prerequisite block (dc-dc-phase4:29-31,43-45). The DR "mirror" vocabulary collision (ceph rbd-mirror vs apt mirror) is a naming hazard only.
  • (g) Cross-DC sequencing: coherent as authored. bundle.yaml:904-912 wires only this DC's ceph-local leg with ceph-remote bound but unrelated (deliberate, docs/dc-dc-deployment-workflow.md:656-662); the peer relationship is established by CLI bootstrap at Stage 6 Step 5 after both DCs exist. Netem is already live on virbr5, so Stage 6 Step 3's check is satisfiable where placed. NOTE: ceph-rbd-mirror will sit peerless from dc0's Stage-5 deploy until Stage 6 -- by design, but no runbook states the expected interim unit status, so an operator may read it as a Stage-5 failure.

LENS 6 UNMEASURED

  • juju restore-backup --help -- NOT RUN, no Juju client on this host. Reported as L6-14 RISK, not as "the command does not exist."
  • juju bind ceph-mon rbd-mirror=replication (dc-dc-phase5:165) -- subcommand and <endpoint>=<space> syntax NOT verified; excluded from L6-7 rather than asserted wrong.
  • juju deploy ... --dry-run merge behaviour of overlays/vr1-dc1-machines.yaml -- NOT RUN (no Juju, no model). The overlay itself flags this at :20-23.
  • Reboot-durability of voffice1's dc0/dc1 transit addressing -- NOT probed; L6-13 is scoped to the missing RECORD, not to a claim that the path is fragile.
  • dc-dc-radosgw-multisite.sh, dc-dc-rbd-mirror.sh, dc-dc-dr-drill.sh run with --help ONLY; runtime lib_net_select_dc behaviour under a real DC argument not exercised.

LENS 1 -- RECORD INTEGRITY / STATUS RECONCILIATION (returned third)

LENS 1's own framing: every finding below is a ruling-vs-surface contradiction -- a RULED decision that a live Stage-5 surface reverses in text -- not a runtime failure.

ID: L1-1 CLAIM: scripts/lib-net.sh's vr1-dc1 arm asserts the OpenStack-layer values are "NOT yet ruled/measured" and unsets them, contradicted by D-134-AMENDED (RULED 2026-07-23) plus the built overlays/vr1-dc1-vips.yaml, and hard-fails Stage 5 at its own Step 1 under set -u. EVIDENCE: scripts/lib-net.sh:128 (vr1-dc1) arm), :152-158 -- comment "OpenStack-layer values (VIP bands, FIP pool, keystone VIP) and the VR0 metal fabric facts ... are NOT yet ruled/measured for vr1-dc1 ... UNSET so any use fails loud under set -u", then unset METAL_INTERNAL_VID METAL_INTERNAL_IFACE / unset VIP_PREFIX_PROVIDER VIP_PREFIX_ADMIN VIP_PREFIX_INTERNAL VIP_COUNT_EXPECT / unset FIP_POOL_START FIP_POOL_END KEYSTONE_VIP_DEFAULT. Against docs/design-decisions.md:4637 (D-134 AMENDMENT, Status RULED 2026-07-23) and overlays/vr1-dc1-vips.yaml. Consumers Stage 5 Steps 7-9 run: scripts/phase-03-admin-openrc.sh, phase-04-network-create.sh, phase-04-network-verify.sh, pre-flight-checks.sh. Runbook mandates the selector for exactly these blocks: runbooks/dc-dc-phase4-juju-bundle-per-dc.md:53-60. BLOCKS-STAGE-5: yes | DISPOSITION: ruling GUARD -- DO NOT MECHANICALLY "POPULATE THE UNSET BLOCK". The arm unsets TWO groups for TWO different reasons. METAL_INTERNAL_VID / METAL_INTERNAL_IFACE are correctly unset: D-133 (ADOPTED 2026-07-23, docs/design-decisions.md:4549) abolished the VLAN-103 / br-internal stack for VR1. Only the VIP/FIP/keystone group is superseded. The ruling required is where the authority lives: populate lib-net's dc1 arm from D-134-amended, or re-point the three phase-0* scripts at overlays/vr1-dc1-vips.yaml. NOT the same item as BLOCKER-1.

ID: L1-2 CLAIM: Phase-4 Step 6's juju deploy names two overlay paths that do not exist and omits all three overlays that constitute the ruled dc1 deploy input; run literally it fails, and with the missing paths dropped it deploys dc0's 11 inline VIPs and no machine retag into dc1. EVIDENCE: runbooks/dc-dc-phase4-juju-bundle-per-dc.md:276-282 names --overlay overlays/octavia-pki.yaml and --overlay "overlays/${DC}-hostnames.yaml". ls overlays/ returns exactly dc-dc-ipv6-family-matrix.yaml dc-ha-scaleup.yaml vr1-dc1-machines.yaml vr1-dc1-vips.yaml. The ruled deploy input is 3 overlays + --dc vr1-dc1 (docs/CURRENT-STATE.md:207-209). bundle.yaml still carries 11 inline dc0 VIPs (:200,239,295,364,400,490,576,603,657,722,780). BLOCKS-STAGE-5: yes | DISPOSITION: DOCFIX

ID: L1-3 CLAIM: Phase-4 Step 4 and its delivery checklist instruct hand-editing bundle.yaml's VIP lines for the second DC, which the 2026-07-25 ruling 3 reversed. EVIDENCE: runbooks/dc-dc-phase4-juju-bundle-per-dc.md:210-214 ("bundle.yaml's VIP lines need editing to DC2's real .50-.60-equivalent band ... a genuine, reviewed bundle edit") and :374-375. Against docs/CURRENT-STATE.md:225-229 (ruling 3: bundle.yaml becomes VIP-free; every per-DC value arrives via overlay). The runbook's own :212 maps DC2 = vr1-dc1, the exact DC Stage 5 deploys. BLOCKS-STAGE-5: yes | DISPOSITION: DOCFIX

ID: L1-4 CLAIM: Phase-4 Step 2's juju bootstrap block carries no controller-tag constraint and still describes the target as a Stage-4 "MAAS-deployed machine" -- both reversed by ruled decisions; run as written it bootstraps onto one of the nine role nodes, the outcome the D-104 amendment explicitly rejected. EVIDENCE: runbooks/dc-dc-phase4-juju-bundle-per-dc.md:136-137 and :174 (juju bootstrap <cloud> <name> -- no --constraints). Against docs/design-decisions.md:2130-2133 (D-104 AMENDMENT ADOPTED 2026-07-24, "Dedicated 10th VM (Recommended)") and :2158-2162 ("juju bootstrap --constraints tags=juju-controller-vr1-dc1 targets it deterministically and no OpenStack tags= role constraint can cross-grab it"). Against DOCFIX-200: docs/CURRENT-STATE.md:48, and the same runbook's already-corrected Prerequisites at :25-28, which Step 2 was not swept with. BLOCKS-STAGE-5: yes | DISPOSITION: DOCFIX (Larger than the recorded fragment: Step 2 also still asserts a Deployed-node target, and the 10th VM is unbuilt, so the constraint has no machine to select today.)

ID: L1-5 CLAIM: Phase-4 Steps 1/2 place the juju session on the jumphost, contradicting D-128's ruled two-plane origin -- juju 3.6.25 lives on voffice1 and was REMOVED from vcloud, so Step 2's first mutation has no binary to run. EVIDENCE: runbooks/dc-dc-phase4-juju-bundle-per-dc.md:119 ("CHECK -- jumphost / wherever this session runs juju against this DC"); grep -n 'voffice1\|headend' on that runbook returns only :148 and :156, both about the MAAS key, never about where juju runs. Against docs/CURRENT-STATE.md:161-162 ("Juju 3.6.25 on voffice1 (headend, D-128; removed from vcloud)") and D-128 Status docs/design-decisions.md:4160. BLOCKS-STAGE-5: yes | DISPOSITION: DOCFIX

ID: L1-6 CLAIM: The phase-4 runbook is written wholly in the pre-D-117 DC1/DC2 namespace, in which the DC Stage 5 deploys (vr1-dc1) reads as "DC2 -- NOT YET ASSIGNED / BLOCKED / STOP" while vr1-dc0 reads as "DC1 -- needs NO VIP/CIDR changes"; D-117/D-119 retired that namespace and lib_net_select_dc mechanically rejects its tokens. EVIDENCE: runbooks/dc-dc-phase4-juju-bundle-per-dc.md:59, :121, :72-79, :81-93 ("DC2's bundle deploy is BLOCKED on this ... STOP here for DC2 and only proceed with DC1"), :127-131, :361-362. Against D-117 Status (docs/design-decisions.md:2996-2997), D-119 Status (:3221), scripts/lib-net.sh:159-161 (bare dc0|dc1|dc2 returns 1, "RETIRED (D-119)"). Against "NOT YET ASSIGNED": docs/dc-dc-netbox-buildout-scope.md:190 (DC2_V4_SUPERNET ASSIGNED (D-115) 10.12.64.0/19); scripts/lib-net.sh:128-138. BLOCKS-STAGE-5: yes | DISPOSITION: DOCFIX (Two readings, both wrong, both destructive: read literally, Stage 5 STOPs on the DC it is meant to build; read by position, vr1-dc1 is treated as "DC1" and gets dc0's 10.12.4/8/12.x VIPs.)

ID: L1-7 CLAIM: Gate row G3 reads OPEN with a standing FREEZE, contradicted by its own cited evidence file and by G11 -- and the FREEZE clause, if believed, blocks the DOCFIX batch this audit is queuing. EVIDENCE: docs/CURRENT-STATE.md:838 ("Batch 6 OPEN: ... PENDING only item 6 ...; FREEZE holds for un-gated surfaces"). Its own cited capture: docs/audit/phase6-exit-runs-20260719.md:84 ("SIGNED 2026-07-19 ... PASS") and :91-92 ("ALL SIX EXIT RUNS PASS ... G3 + G11 CLOSED"). Corroborated by docs/CURRENT-STATE.md:846 and :1249-1253. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX (No choice required -- two surfaces already declare G3 CLOSED. The consequential half is the FREEZE clause, not the state token.)

ID: L1-8 CLAIM: G17's closing condition omits the node time-source check that two other surfaces assign to G17, so G17 could close as written while the DoD bullet-6 replacement is never verified -- and the observation window is one-time. EVIDENCE: docs/CURRENT-STATE.md:852 (G17 [V] column) lists only the dc0 curl -sI and the dc1 proxy fetch -- no time check. Against docs/dc-dc-deployment-workflow.md:206 ("Node-side reachability and the node time source are gate G17") and runbooks/dc-dc-phase4-juju-bundle-per-dc.md:44-45 ("both: chronyc sources shows the MAAS-served time source, NOT the DC edge (D-129(iv))"). The authority also self-contradicts on bullet 6: docs/CURRENT-STATE.md:52 says "bullet 6 STRUCK" while :342-347 says it "needs a DOCFIX re-expressing it as MAAS-hierarchy time verification". Runbook :48-50: "If first boot happens without these captures being taken, the observation window has passed". BLOCKS-STAGE-5: no | DISPOSITION: ruling (The choice: is MAAS-hierarchy time verification STRUCK, folded into G17's [V] text, or its own row? GA-R6 E3 forbids resolving it by conditional close.)

ID: L1-9 CLAIM: Stage 5's stated entry gate -- "preflight.sh PASS" -- cannot be met as written, because preflight already exits 1 for reasons Stage 5 does not clear. EVIDENCE: runbooks/dc-dc-phase4-juju-bundle-per-dc.md:186-192 ("Expect PREFLIGHT: PASS"); docs/dc-dc-deployment-workflow.md:221 (Stage 5 Gate cell); runbook :354-357. Against docs/CURRENT-STATE.md:999-1003. overlays/octavia-pki.yaml confirmed absent this session. BLOCKS-STAGE-5: yes | DISPOSITION: ruling (Requires an operator choice -- on what recorded basis Stage 5 proceeds against a red preflight, or which named sub-checks must go green first.)

ID: L1-10 CLAIM: docs/dc-dc-deployment-workflow.md carries a full stage/build STATUS table plus a Stage-5 authoring-status cell (GA-R1 violation), whose rows assert dc1's addressing unassigned and its substrate unbuilt -- compounding L1-6, because the skill routes VR1 work to this doc BEFORE the runbooks. EVIDENCE: docs/dc-dc-deployment-workflow.md:871 ("## Where things stand today (2026-07-09)") with rows "Stages 3-7 NOT executed", "tofu plan/apply for the Stage 3 DC substrate is still UNEXERCISED", "opentofu/ (DC2 planes) | not done", "DC1/DC2 still have NO uplink network"; and :224 ("DC2 is hard-blocked pending its NetBox literals"). Against docs/CURRENT-STATE.md:39-55 and scripts/lib-net.sh:128-138. Routing: SKILL.md:87. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX (Mechanical fix = demote to pointers per GA-R1, not re-date. Deliberately scoped: NOT reporting the rest of that table, the register's OPNsense staleness, opentofu/README.md:187, or docs/dc-dc-netbox-buildout-scope.md:155 -- cleanup under the GA-F06 bound. Checked and explicitly NOT a finding: the workflow doc's Stage-6 claim that ceph-mon's rbd-mirror binding sits on storage is stale -- bundle.yaml:544 reads rbd-mirror: replication, corrected by DOCFIX-167.)

ID: L1-11 CLAIM: opentofu/variables.tf asserts dc1's planes are deferred pending a NetBox assignment, two variables above the ratified dc1 plane values in the same file. EVIDENCE: opentofu/variables.tf:34 against :61-67 ("D-124 AMENDMENT 2026-07-21, addressing RATIFIED ... apex-VERIFIED, not invented"). BLOCKS-STAGE-5: no (Stage 5 runs no tofu) | DISPOSITION: log-only

ID: L1-12 CLAIM: Next-free numbers derive independently to D=138, DOCFIX=205, BUNDLEFIX=053, matching ledger-scan.sh exactly -- the section-9 self-inflation failure mode is NOT currently biting. EVIDENCE: D header-authoritative: grep -ohE '^## D-[0-9]+' docs/design-decisions.md -> highest 137 (125 headers). Unfiltered token scans returned DOCFIX-...201 202 203 204 777 888 and BUNDLEFIX-...050 051 052 100 777; the 777/888/100 values are deliberate harness fixtures occurring only in tests/ledger-scan/run-tests.sh:84,91,92. True highest DOCFIX 204 / BUNDLEFIX 052. BLOCKS-STAGE-5: no | DISPOSITION: log-only

ID: L1-13 CLAIM: All four PROPOSED/OPEN decisions are correctly NOT gating Stage 5 -- but D-136's non-gating verdict applies to its mechanism only. EVIDENCE: D-068 remainder is Q2 at Roosevelt Vault design time; bundle.yaml:154 pins channel: 1.8/stable per the ruled Q1. D-131 sub-1/2 RULED and built; sub-4 pinned to next-deployment design time. D-132 Status PROPOSED/OPEN, operator-pinned to the NEXT DEPLOYMENT (:4439). D-136 Status PROPOSED, docs/CURRENT-STATE.md:246 "Does NOT gate the dc1 deploy". HOWEVER D-136's own problem statement (:4778-4788) enumerates defects that ARE Stage-5 gating and tracked elsewhere: four disagreeing app-to-VIP lists, two overlays owning vip: for the same 10 apps under per-key REPLACE last-wins so the deploy input depends on overlay ORDER, and vault carrying no vip: while dc-ha-scaleup.yaml declares cluster_count: 3. BLOCKS-STAGE-5: no | DISPOSITION: log-only

LENS 1 UNMEASURED

  1. timeout 240 bash scripts/preflight.sh -- DENIED by the Claude Code auto-mode classifier. Preflight's current live exit code and red set are UNMEASURED by this lens; L1-9 rests on the recorded measurement at docs/CURRENT-STATE.md:999-1003. [RESOLVED BY THE AUDIT SESSION -- see `docs/audit/stage5-live-measurement-20260727.txt` section 3: preflight measured exit 1 with the red set EXACTLY the known one, nothing new. Root cause of the denial: the session allow-list has no `Bash(timeout *)` rule, so the command fell through to the classifier -- the same failed-to-MATCH class recorded on 2026-07-26, not a classifier override.]
  2. Gate rows G1-G13 and G16 (all CLOSED) not walked for evidence-path existence -- task scoped (c) to non-closed rows plus G17. Rows walked (G3, G14, G15, G17) all resolve, with one exception: G14's cell describes overlays/octavia-pki.yaml as a live in-clone exposure, but the file is absent from this working tree. Not raised as a finding -- it is a SEC-row description, not a Stage-5 decision input.
  3. Live cloud state not probed -- out of lens scope; every claim above is repo-surface-vs-repo-surface.
  4. overlays/vr1-dc1-vips.yaml / vr1-dc1-machines.yaml confirmed to EXIST but contents not parsed against D-134's bands -- lens 3's assertion to make.

LENS 2 -- AS-BUILT vs LIVE MEASUREMENT (returned fourth)

ID: L2-1 CLAIM: The bundle's Ceph OSD device does not exist on any VR1 node in either DC -- bundle.yaml sets osd-devices: /dev/vdb, but every one of the 18 node VMs has exactly ONE block device (vda), and modules/node-vm is hard-coded to a single disk, so no second disk can appear without a module change. EVIDENCE: ssh voffice1 "ssh 172.31.0.2 'virsh -c qemu:///system domblklist vr1-dc0-storage-01'" -> vda vr1-dc0-storage-01-disk.qcow2 only. Identical single-vda for vr1-dc0-storage-0{1..4}, control-01, compute-01, and via 172.31.0.6 for vr1-dc1-storage-01, storage-04, control-01. MAAS agrees for all 18: physicalblockdevice_set length = 1, name = vda (590GB) on 18/18 rows. Contradicts bundle.yaml:560 -- osd-devices: /dev/vdb # libvirt-attached, MAAS-untracked, wiped pre-deploy (a VR0 as-built comment; VR0 hosts had an attached vdb, VR1 nodes never did). Root cause in-config: opentofu/modules/node-vm/main.tf:104-125 declares exactly one devices.disks[] with target.dev = "vda" from the single libvirt_volume "disk" (main.tf:26). grep -rn "osd\|vdb\|extra_disk" opentofu/vr1-dc0-substrate/ opentofu/vr1-dc1-substrate/ returns only disk_size_bytes -- no OSD disk variable exists in either substrate root. BLOCKS-STAGE-5: yes | DISPOSITION: ruling (add an OSD volume to modules/node-vm and re-apply both substrates, vs re-point osd-devices at a directory/partition path, vs re-shape the storage role -- each has a different Roosevelt delta)

ID: L2-2 CLAIM: D-134's .4-.49 RESERVED band and .50-.99 VIP band are reserved in PROSE ONLY -- MAAS holds ZERO reserved ipranges cloud-wide and reports the entire VIP band as allocatable on all 12 VR1 DC plane subnets. The tooling that creates these reservations refuses to run for any non-VR0 DC, so no VR1 path to create them exists. EVIDENCE: ssh voffice1 "maas admin ipranges read" -> exactly three ranges, ALL type=dynamic: 10.10.1.100-.200, 10.12.68.201-.254, 10.12.8.201-.254. Zero type=reserved. maas admin subnet unreserved-ip-ranges <id> for all 12 DC plane subnets shows the .50-.99 band inside MAAS's allocatable pool on 12 of 12 (e.g. id=6 10.12.8.0/22 UNRESERVED 10.12.8.5 - 10.12.8.99; id=10 10.12.64.0/22 UNRESERVED 10.12.64.3 - 10.12.64.99). Only node statics and the .201-.254 dynamic ranges are protected. Contradicts docs/design-decisions.md:4654-4655 (D-134 AMENDMENT table: .4-.49 RESERVED, .50-.99 VIP band). Corroboration this is a VR1 gap not a design choice: scripts/phase-00-maas-standup.sh:255 and its VR0 plane table (:118-120) reserve the API-VIP bands + D-003 FIP pool for VR0; none exist for either VR1 DC, and :136 refuses outright (FAIL: PLANES table is DC0-hardcoded ... refusing to plan another DC's scheme). Downstream hard gate: scripts/phase-04-network-verify.sh:100 fails if the FIP pool is not a reserved iprange; for vr1-dc0 that pool (10.12.5.0-10.12.7.254, lib-net.sh:65-66) is measured absent. BLOCKS-STAGE-5: yes | DISPOSITION: ruling (boundaries already ruled by D-134/D-058, but creating them is a live MAAS mutation on 12 subnets and needs gating; whether to carve the FIP pool now or at phase-04 is a sequencing choice)

ID: L2-3 CLAIM: There is NO IPv6 anywhere in the VR1 DC substrate -- zero IPv6 subnets on any of the 12 DC plane fabrics and zero IPv6 addresses on all 18 nodes -- while D-101's 2026-07-25 RULING NOTE CLOSED the v4-only option for BOTH DC0 and DC1 in this deployment. EVIDENCE: maas admin subnets read | jq '.[]|select(.cidr|contains(":"))' -> exactly ONE v6 subnet cloud-wide, 2602:f3e2:f01:100::/64 on fabric-0 (the Office1 base net), space undefined. None of the 10 named plane fabrics nor the two metal-admin fabrics carries an IPv6 subnet. Zero IPv6 links across all 18 nodes; every node reports default_gateways.ipv6 = NONE (IPv4 gw 10.12.4.1 / 10.12.64.1). Contradicts docs/design-decisions.md:2034-2051 -- RULING NOTE 2026-07-25, operator verbatim "Dual stack to be used where IPv4 is required, IPv6 where IPv6 only makes sense" and "Dual stack deployment for DC0 and DC1. This is the deployment when the dual-stack is added"; Effect: "the v4-only phasing option ... is CLOSED, for BOTH DC0 and DC1 in this deployment." D-101's family matrix (:2015-2016) requires ULA on data-tenant, storage, replication and a ULA leg on metal-admin/metal-internal -- none has any MAAS v6 presence to bind against. BLOCKS-STAGE-5: yes | DISPOSITION: ruling (D-101's own "Remaining open item" at :2032 is the un-assigned NetBox literals -- org ULA /48 and per-DC GUA carve. Those must be assigned and carved into MAAS before a dual-stack deploy; the alternative is re-opening the CLOSED v4-only phasing.)

ID: L2-4 CLAIM: All three rack-side checkers emit a confident, definitive FAIL when invoked in the literal form the routing table gives (bash scripts/<name>.sh check <site> from the repo root on the jumphost) -- they silently evaluate the LOCAL host instead of refusing. All three PASS when actually piped to their rack. A false RED on dc-mirror.sh check dc1 is precisely what invites the install that CURRENT-STATE documents as destructive. EVIDENCE: From the repo root on vcloud: bash scripts/dc-mirror.sh check dc0 -> 15 MISS lines, FAIL, EXIT=1; dc-cache-proxy.sh check dc1 -> 12 MISS, FAIL, EXIT=1; dc-rack-net.sh check dc0 -> 8 MISS, FAIL, EXIT=1. Run correctly on the rack: ssh voffice1 "ssh 172.31.0.2 'sudo -n bash -s -- check dc0'" < scripts/dc-mirror.sh -> OK 10.12.8.4/22 on virbr2, OK mirror answers http://10.12.8.4/ (200), OK last-sync: OK 2026-07-27T08:43:46Z ubuntu=0 uca=0, PASS; dc-cache-proxy.sh on dc1 -> PASS; dc-rack-net.sh -> PASS on both racks. The scripts state the requirement in prose but do not enforce it (scripts/dc-rack-net.sh:8). The copy-pasteable form is SKILL.md:97, which renders the bare local command as the backticked answer with the transport caveat later in the cell. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX (mechanical -- a host-identity precondition that REFUSES with a distinct exit code when the expected rack markers are absent, rather than reporting FAIL; the "unrecognised state refuses" rule applied to the RED side)

ID: L2-5 CLAIM: The DC plane bridges are jumbo (MTU 9000) on both racks, but every MAAS VLAN -- including all 10 named plane fabrics -- records MTU 1500, and neither bundle.yaml nor any overlay carries a single MTU option; D-101's mandatory MTU budget is neither achieved nor declared anywhere the deploy will read. EVIDENCE: maas admin fabrics read -> 17/17 VLANs report mtu 1500 (all five dc0 plane fabrics, all five dc1, fabric-4, fabric-142, ...). On the racks: ip -o link show -> enp1s0 mtu 1500 (rack transit leg), virbr1..virbr6 mtu 9000 (the six plane bridges), same on both. grep -n -i "mtu" bundle.yaml overlays/*.yaml -> no output. Contradicts docs/design-decisions.md:2025 (D-101 Tenant/MTU sub-policy: raise the underlay to jumbo end-to-end so tenant MTU stays 1500, or if pinned at 1500 tenant MTU drops to ~1444 and MUST be set consistently across ovn geneve, tenant-network MTU and amphora; "The measured underlay MTU is a Phase-0 gate -- do not assume jumbo"). Measured state is NEITHER branch: jumbo bridges, 1500 VLAN records, 1500 rack transit (so cross-DC replication is not jumbo end-to-end), no MTU on any charm. scripts/dc-dc-mtu-geneve-budget.sh exists but has never been run to a recorded verdict; invoked bare it correctly refuses (FAIL: --underlay-mtu is REQUIRED). BLOCKS-STAGE-5: no (the deploy succeeds; the failure surfaces later as tenant/geneve blackholing -- D-101 names it "the classic nested-OpenStack failure mode") | DISPOSITION: ruling

ID: L2-6 CLAIM: scripts/lib-net.sh declares a metal-admin gateway for both VR1 DCs that does not exist -- MAAS records no gateway on either metal-admin subnet, and nothing answers ARP or ICMP at either address. EVIDENCE: maas admin subnets read -> 10.12.8.0/22 none, 10.12.68.0/22 none (control: 10.12.4.0/22 10.12.4.1, 10.12.64.0/22 10.12.64.1). ping -c2 -W2 10.12.8.1 from the dc0 rack -> 100% loss, ip neigh FAILED; same for 10.12.68.1 from dc1. Control: both provider-public gateways answer 0% loss, ARP REACHABLE, and both racks' default route goes via them. Contradicts scripts/lib-net.sh:37 (PLANE_GW includes ["10.12.8.0/22"]="10.12.8.1", inherited verbatim by the vr1-dc0 arm at :112-127) and :149 (the vr1-dc1 arm's own ["10.12.68.0/22"]="10.12.68.1"). The 10.12.8.1 value traces to VR0's real as-built (phase-00-maas-standup.sh:119); VR1's edges carry only a provider-public LAN leg, so metal-admin has no router in either DC. Consumer that would trip: scripts/pre-flight-checks.sh:121-124 hard-fails on gateway=$gw (want $exp). BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX (the vr1-dc1 arm should not carry a metal-admin gateway, and the vr1-dc0 arm's inheritance needs the same caveat treatment lib-net.sh:120-126 already applies to METAL_INTERNAL_VID/METAL_INTERNAL_IFACE)

ID: L2-7 CLAIM: The D-104-amendment 10th controller VM does not exist in either DC and no juju-controller-vr1-dc* MAAS tag exists -- measured confirmation of a recorded pending item. EVIDENCE: virsh list --all on each rack -> exactly 9 node domains (all shut off) + 1 running edge per DC; no 10th VM. MAAS holds 20 machines (18 VR1 nodes + office1-netbox + office1-tailscale), none with a controller tag; measured tag set is the 5 already reported. BLOCKS-STAGE-5: yes | DISPOSITION: log-only (already recorded as gated pending work; measured confirmation, do not double-count)

LENS 2 CONFIRMED AGAINST LIVE (no finding -- the record is RIGHT)

  • 18 nodes, all Ready, 9 per DC, shapes EXACT to D-121 Option C: 3x16cpu/65536MiB + 2x12cpu/49152MiB + 4x8cpu/24576MiB per DC; 18/18 power_type=virsh.
  • All 18 pinned boot MACs match scripts/lib-hosts.sh:118-126 and :141-149 exactly, cross-checked tofu-name -> MAC -> live system_id via power_id.
  • VIRSH_POWER_ADDRESS matches live for all 18 (qemu+ssh://jessea123@172.31.0.2/system dc0 9/9, ...@172.31.0.6/system dc1 9/9). lib-hosts.sh:127 and :150 correct.
  • 17 fabrics -- CURRENT-STATE:349 verified exactly. Survivors: 10 named plane fabrics, fabric-4/fabric-142, fabric-0/fabric-1, fabric-2/fabric-141, fabric-3. No 192.168.1.0/24, no fabric-5.
  • 6 spaces, 2 subnets each, 12 VLANs space-assigned, all vid=0 untagged -- the D-133 flat carve holds.
  • 7 interfaces per node, ZERO orphans, 18/18: enp1s0..enp6s0 + br-ex. enp2s0 correctly carries no link (D-100 provider-raw); br-ex is a bridge over enp2s0 holding the provider-public static.
  • D-134 statics perfect: one octet per node identical across all 6 planes, 6 links each, 18/18 -- control .100/.101/.102, compute .120/.121, storage .150-.153, both DCs.
  • Rack legs + D-131 forwarder up on both racks (dc-rack-net.sh check PASS both). Forwarders live-probed: dig @10.12.8.3 and @10.12.68.3 NOERROR for maas-internal, archive.ubuntu.com, streams.canonical.com.
  • Both artifact paths PASS on their own hosts. Both DC edges running and routing at 0% loss.
  • Boot images: ubuntu/jammy amd64/ga-22.04 + 5 jammy variants all Synced, plus noble.

LENS 2 UNMEASURED

  1. Whether MAAS would in FACT allocate a Juju/LXD container address out of the unreserved .50-.99 band (L2-2) -- behavioural, only observable during a real deploy. What IS measured is MAAS's own declaration that the band is unreserved on 12/12 subnets; no claim is made about allocation order.
  2. The three tofu plan zero-diff captures -- not attempted by this lens. [DONE BY THE AUDIT SESSION: all three ZERO DIFF, see `docs/audit/stage5-live-measurement-20260727.txt` section 1.]
  3. Node-side anything -- all 18 nodes powered off in Ready; gate G17's territory by construction.
  4. site-baseleg.sh check office1 -- outside this lens's bound. [DONE BY THE AUDIT SESSION: PASS.]
  5. IPv6 state at the NetBox apex and on the two DC edges -- MAAS and nodes only were measured. L2-3 is scoped to MAAS + node reality and does NOT assert the apex is empty.
  6. maas CLI reachability from the jumphost itself -- every MAAS read went through ssh voffice1; contributes nothing to the recorded "MAAS unreachable from the jumphost" preflight red.
  7. dc1 rack bridge-to-network name mapping -- MTUs measured by index; only virbr6=metal-admin and virbr4=provider-public resolved by name. The 9000/1500 finding does not depend on the unmapped ones.
  8. Whether serial-console / pod-console-logging tags are MEANT to be on the VR1 nodes -- measured that they are not; no ruling found requiring them, but not exhaustively searched.

LENS 7 -- ROOSEVELT-DELTA / GOAL ALIGNMENT (returned fifth)

ID: L7-1 CLAIM: Stage 5's Juju work executes on the headend (voffice1), but D-137's absolute discovery bound declares ~/vault-init/*, ~/octavia-pki/* and ~/admin-openrc on the jumphost only -- so every credential Stage 5's bundle deploy mints lands at a location the register is FORBIDDEN to visit, reproducing SEC-022 at the scale of the whole control plane. EVIDENCE: creds-manifests/vm-secret-locations:54-56,74-78 declare those five paths as jumphost ... local; the headend block :83-92 contains only ~/vr1-dcN-creds/*, /root/maas-secrets/*, ~/snap/maas/current/.maascli.db, ~/.local/share/juju/*, /var/snap/maas/current/root/.ssh/*, /var/snap/maas/common/maas/secret -- no vault-init, no octavia-pki, no admin-openrc. D-137 sub-ruling 3 (operator utterance "Declared locations only") makes that list ABSOLUTE: "it never walks outside the list". D-128 fixes Plane-2 execution on voffice1 (docs/design-decisions.md:4176-4180); SEC-018 (docs/security-ledger.md:32) already records the consequence. Jumphost has no juju: docs/audit/preflight-20260727-stage5-audit.txt:49. BLOCKS-STAGE-5: yes | DISPOSITION: DOCFIX [AUDIT-SESSION CONFIRMATION: `ssh voffice1 'command -v juju'` -> `/snap/bin/juju`; on vcloud `command -v juju` -> ABSENT. `~/admin-openrc`, `~/vault-init`, `~/octavia-pki` all ABSENT on voffice1 today. `~/.local/share/juju/` exists on voffice1 with `clouds.yaml`, `credentials.yaml`. Premise CONFIRMED.]

ID: L7-2 CLAIM: The credential register carries ZERO rows for what Stage 5 actually mints; the vault/Octavia/openrc rows are singleton under vr0-phase0N mint-stages that stages-reached marks pending, so P5 emits a green "deferred as not-yet-minted" straight through the largest mint of the deployment, and the per-DC symmetry gate is structurally incapable of firing on them. EVIDENCE: creds-matrix.tsv -- all 14 vault/Octavia-PKI/openrc/vault-ca rows are cardinality=singleton, site-key=-, mint-stage in {vr0-phase01,vr0-phase02,vr0-phase03}; creds-manifests/stages-reached marks all three pending, so flipping stage5 to reached never makes them expected. The only 8 mint-stage=stage5 rows are dcN-maas-apikey / dcN-juju-maas-user / juju-client-clouds -- already minted 2026-07-24 (SEC-018/-019), not new Stage-5 output. Symmetry gate: scripts/creds-matrix.py:380 if r.site_key != dc or r.cardinality != "per-DC": continue. Measured green: docs/audit/preflight-20260727-stage5-audit.txt:85 [ok] E1 18 expected artifact(s) deferred as not-yet-minted. Both operator branches fail closed-eyed: runbooks/phase-02-vault-bringup.md:69,71 (mkdir -p ~/vault-init; ... | tee ~/vault-init/init.txt) collides two DCs' unseal shares at one fixed path on an irreversible one-shot; runbooks/dc-dc-phase4-juju-bundle-per-dc.md:229-232's "Store them separately, clearly labeled by DC" puts material at a path vm-secret-locations does not list -- and scripts/phase-03-admin-openrc.sh:31 still reads the fixed CA="${CA:-$HOME/vault-init/vault-ca-root.pem}". BLOCKS-STAGE-5: yes | DISPOSITION: DOCFIX

ID: L7-3 CLAIM: The .50-.60 VIP band, provider-ext/FIP pool and reserved-CIDR values that Stage 5 Steps 7-9 write into vr1-dc1 come from scripts that source lib-net.sh and NEVER call lib_net_select_dc, so they silently use VR0/dc0's 10.12.4/8/12/16/32/36 literals against a DC whose planes are 10.12.64-84. EVIDENCE: measured over all 27 lib-net.sh consumers -- only 6 reference the selector at all. scripts/phase-04-network-create.sh:24, phase-04-network-verify.sh:35, phase-03-core-verify.sh, phase-05-octavia-verify.sh, pre-flight-checks.sh, juju-spaces-check.sh:17, tenant-onboard.sh:183, tenant-acceptance.sh, tenant-offboard.sh all source unconditionally with zero selector references and expose no $DC hook. lib-net.sh:22 sets VR0 defaults; :137-146 are dc1's divergent values. Safety is opt-in by construction -- lib-net.sh:76-78 "sourcing this file with no further action continues to populate PLANE_CIDRS ... exactly as above (VR0/DC0's real, measured values)"; the dc1 arm's fail-loud unset guard (:155-157) only fires if the selector is CALLED. Remediation pattern exists and was applied to just three scripts (scripts/carve-host-interfaces.sh:48-67, DOCFIX-166). runbooks/dc-dc-phase4-juju-bundle-per-dc.md:119-125 has the operator call the selectors in their OWN shell -- a variable no child bash scripts/... process inherits, and which each script overwrites by re-sourcing. BLOCKS-STAGE-5: yes (the vr1-dc1 arm; harmless for vr1-dc0 under D-101 value-for-value inheritance) | DISPOSITION: DOCFIX

ID: L7-4 CLAIM: D-128 classifies the INNER tofu roots as Plane 2 -- "what we REHEARSE for Roosevelt" -- while every one of their five modules is libvirt-substrate creation that the shim register says has NO Roosevelt analog; a Roosevelt session greping design-decisions would treat opentofu/vr1-dcN-substrate/ as transferable production IaC, which the workflow doc explicitly forbids. EVIDENCE: docs/design-decisions.md:4176-4180 (D-128 Plane 2) names "the INNER tofu root" alongside MAAS/NetBox/tenant tests as the rehearsed half; carried as a standing invariant at SKILL.md:123-127. Actual content of opentofu/vr1-dc1-substrate/main.tf:24,33,46,57,142 = dc-storage-pool, dc-planes, wan-bridge, opnsense-edge, node-vm. 11 of 12 modules are dmacvicar/libvirt. docs/dc-dc-deployment-workflow.md:157 on that same artifact: "Explicitly tagged shim: node-VM creation has no Roosevelt analog ... do not treat as reusable production IaC." The two boundaries differ by an entire tofu root. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

ID: L7-5 CLAIM: The Section-9 shim register has not been maintained since 2026-07-09, and the workflow doc's exhaustive claim ("the ONLY deliberate no-Roosevelt-analog steps are the Section 9 shim register") is now FALSE -- at least six VR1-only mechanisms have accumulated outside it. EVIDENCE: docs/dc-dc-buildout-design.md:199-210 lists exactly four items; docs/dc-dc-deployment-workflow.md:12-13 makes the exhaustive claim. Absent from the register, each measured: (i) D-128 Plane 1, self-declared "No Roosevelt analog" at docs/design-decisions.md:4172; (ii) the DC containment VM, "a deliberate simulation-only delta" at docs/dc-dc-deployment-workflow.md:87; (iii) scripts/site-baseleg.sh:4-27; (iv) scripts/site-forward.sh:4-13; (v) scripts/dc-rack-net.sh:17-22 (the rack-legs half; the D-131 dnsmasq half at :23-32 genuinely DOES transfer, and the script does not distinguish them); (vi) scripts/osd-blank-check.sh:5,21-25. Calibration counter-examples that ARE correctly tagged: scripts/sudoers.d/netem-tc:25 and scripts/maas-node-power.sh:23-25. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

ID: L7-6 CLAIM: Stage 5 cannot start phase-01 Step 1.0 without an unmade operator decision on whether the two DCs share one Octavia CA -- and the reuse branch would put a single amphora control-plane CA private key across two clouds that D-100 defines as independent, which is the wrong answer for hard tenant isolation. EVIDENCE: runbooks/dc-dc-phase4-juju-bundle-per-dc.md:204-208 ("this is a call the operator should make explicitly ... not silently default to reuse") -- correctly flagged, but UNMADE. Contrast the ruled position one step later at :225-227: "Per D-109: each DC's Vault is its OWN independent root CA -- no regional root-of-trust this phase." overlays/octavia-pki.yaml is a single unscoped repo-clone path holding two CA private keys plus a plaintext issuing-CA passphrase, in a repo SEC-004 records as currently PUBLIC. BLOCKS-STAGE-5: yes | DISPOSITION: ruling

ID: L7-7 CLAIM: The credential reproducibility debt is real and measured, but its sharp edge is VR1-PRESENT, not Roosevelt-future: SEC-007/-015 make edge SSH the only management path, so a jumphost rebuild locks the operator out of both DC edges TODAY -- while creds-mint.sh remains unbuilt and the checker reports the debt as [ok]. EVIDENCE: measured on creds-matrix.tsv: 30 rows across 16 distinct ids carry mint-ref=operator-terminal. Origin figure is different accounting -- docs/audit/creds-creation-points-20260725.md FINDING 1 counts 12 declared secrets with no mint command, from grep -rnI "ssh-keygen" . returning ZERO hits repo-wide. Gate reports it non-blocking: preflight-20260727-stage5-audit.txt:77 [ok] S4 provenance debt: 30 row(s) ... Admitted by design. scripts/creds-mint.sh does not exist. ASSESSMENT -- minimum fix by SHAPE, not by inventing a command: (1) for the six SSH keypairs and the OPNsense root password/hash, record the mint invocation as a numbered runbook step and flip those rows' mint-ref from operator-terminal to runbook:<path>:<step>; the S4 check already resolves runbook: references, so the debt becomes convergent WITHOUT a new tool. (2) Do the six edge/service/power keys FIRST -- their loss is unrecoverable-in-place. (3) creds-mint.sh is orthogonal: it prevents the NEXT unregistered mint, it does not retroactively make an existing key reproducible, so it should not gate this. BLOCKS-STAGE-5: no | DISPOSITION: ruling

ID: L7-8 CLAIM: Deploying Stage 5 with the apex incomplete is NOT now-or-never for the D-136 generator, but it IS now-or-never for the authority DIRECTION: the 33 VIPs become as-built Keystone endpoints and cert SANs, after which NetBox can only be back-filled to match the deploy, permanently inverting "NetBox is the IPAM apex". EVIDENCE: D-136 (docs/design-decisions.md:4761+) is PROPOSED/unruled; its own option (C) argues hand-rendering first is what makes the front half "testable BY REPRODUCTION", so a generator is genuinely not now-or-never. What Stage 5 FORECLOSES: overlays/vr1-dc1-vips.yaml:16-45 fixes 33 dc1 VIPs; once hacluster owns them and Keystone endpoints / Vault-issued SANs are registered against them they stop being an editable literal. Stage 5 has no wiring to the apex at all: grep -n "D-136\|D-134\|apex\|netbox" runbooks/dc-dc-phase4-juju-bundle-per-dc.md returns one incidental hit (:211). BLOCKS-STAGE-5: no | DISPOSITION: log-only

ID: L7-9 CLAIM: The substrate's declared INPUT values are the one deploy-artifact class the repo does not carry -- *.auto.tfvars is gitignored under a rationale written for STATE files -- so the runbooks-and-scripts-as-primary-deliverable property does not hold for opentofu/. EVIDENCE: .gitignore:75-76 opentofu/**/*.auto.tfvars + .auto.tfvars.json; git ls-files | grep tfvars returns nothing, and no .example/template is tracked. Two live tfvars sit untracked on disk (opentofu/dc-dc-phase0.auto.tfvars, opentofu/d124-rack.auto.tfvars), and the inner roots' tfvars live on voffice1. The ignore block's stated reason (.gitignore:63-70, DOCFIX-175) is about tfstate storing sensitive attributes in plaintext, and explicitly records "never pass secrets via -var" -- i.e. tfvars carry no secrets by this repo's own rule, so nothing in the rationale covers them. Consequence: the ZERO-DIFF tofu plan expectation depends on artifacts a fresh clone does not have. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

ID: L7-10 CLAIM: lib-net.sh's vr1-dc1 arm still unsets KEYSTONE_VIP_DEFAULT/VIP_PREFIX_*/FIP_POOL_* as "not yet ruled/measured", but those values have since arrived in overlays/vr1-dc1-vips.yaml. EVIDENCE: scripts/lib-net.sh:152-157 vs overlays/vr1-dc1-vips.yaml:16 keystone: vip: "10.12.64.50 10.12.68.50 10.12.72.50". Sequencing gap, not a contradiction: the guard was correct when written and has not been closed. KEYSTONE_VIP_DEFAULT is consumed by the tenant-* family (scripts/tenant-onboard.sh:19) and phase-03/06. [Same underlying item as L1-1; L7-10 adds the consumer list.] BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX

LENS 7 UNMEASURED

  1. Whether any repo timeout/wait/sizing constant was widened for depth-4 nested I/O and is now baked in without a VR1-only note. No constant found documented as nested-virt-calibrated; that is not evidence none exists. Unqualified candidates: scripts/phase-05-amphora-pipeline.sh:43 RETROFIT_WAIT="${RETROFIT_WAIT:-30m}" (runs at Stage 5 Step 9 on depth-4 nested compute; provenance of 30m not established) and scripts/site-baseleg.sh:52-55 BRIDGE_WAIT=60.
  2. Live confirmation that the Stage-5 execution host is voffice1. [DONE BY THE AUDIT SESSION -- see the L7-1 confirmation note above.]
  3. Whether runbooks/dc-dc-phase4-juju-bundle-per-dc.md:119 is a known DOCFIX or an unrecorded contradiction of D-128 -- the DOCFIX register was not grepped for an existing entry.

AUDIT-SESSION FINDINGS (measured by the session itself, not by a lens)

ID: S-1 CLAIM: The openstack client is ABSENT on BOTH the jumphost and the headend, and TEN Stage-5/6/7 scripts require it -- so every post-deploy step from phase-03 onward cannot run anywhere today. EVIDENCE: command -v openstack on vcloud -> ABSENT; ssh voffice1 'command -v openstack' -> ABSENT. ssh voffice1 'snap list' shows only core24, juju, lxd, maas, postgresql, snapd -- no openstack client. Consumers: grep -ln 'openstack ' scripts/phase-0*.sh -> phase-03-admin-openrc.sh, phase-04-network-create.sh, phase-04-network-verify.sh, phase-04-internal-cert-san-verify.sh, phase-05-amphora-pipeline.sh, phase-05-octavia-verify.sh, phase-06-bootstrap.sh, phase-06-capi-stack.sh, phase-06-mgmt-vm.sh, phase-06-net-setup.sh. No lens found this and no repo surface records it. BLOCKS-STAGE-5: yes (from Step 7 onward) | DISPOSITION: DOCFIX (install/record the client on the ruled Plane-2 host; the WHERE follows from D-128, so no new choice is required)

ID: S-2 CLAIM: Juju on the headend is 3.6.27, not the 3.6.25 the record carries -- an in-channel patch refresh that D-071 permits but that leaves CURRENT-STATE's pin stale, and it is the version that will bootstrap the controller. EVIDENCE: ssh voffice1 'snap list' -> juju 3.6.27 rev 35621 3/stable. Against docs/CURRENT-STATE.md:161-162 ("Juju 3.6.25 on voffice1") and the section-7 pin row ("Last recorded VR0 value 3.6.25 -- historical, unverified here"). D-071 ADOPTED 2026-07-21 rules patch-only controller jumps and in-channel-only refreshes, so 3.6.25 -> 3.6.27 within 3/stable is POLICY-COMPLIANT; the defect is only that the record was not updated. GA-R1 amendment C2: the measurement wins and corrects the document in the capture's commit. BLOCKS-STAGE-5: no | DISPOSITION: DOCFIX